5-8PPM BESS Battery Pack Assembly Line Turnkey Solution For 314AH 587AH 628AH
5-8ppm BESS Production Line 100AH-628AH
Technical file

1. Project Overview
1.1 Project
This project aims to realize a semi-automated BESS assembly line, covering multiple assembly processes from cell feeding to PACK module offline. It is designed to meet model changeover requirements for compatible products, enabling production switching across different product variants and delivering a turnkey solution.
1.2 Process Flow
Cell and Module Section
- Robot cell feeding into sorting machine → OCV testing and sorting → Cell adhesive application and stacking → Module extrusion bundling → Polarity detection → CCD addressing/ Pole cleaning → Manual busbar installation → Laser welding → Post-weld dust removal/inspection → Module EOL Testing → Module offline
PACK Section:
- PACK Enclosure Line → Air tightness Testing → Module Hoisting into Case → Module Fixation and Series Connection → Busbar Installation and BMS Installation → Plug-in Harness Connection and BMU Installation → Top Cover Installation → PACK EOL Testing → PACK Offline
1.3 Line Parameter
| No. | Item | Parameter | Remarks |
|---|---|---|---|
| 1 | Overall Line Efficiency | Cell Sorting: 8 PPM | Automatic Equipment Only, Reference Product |
| 2 | Failure Rate | ≤2% | Counting Equipment-Related Causes Only |
| 3 | Changeover Time | ≤ 2 operators, 5 hours (old model, excluding first Pcs time) | Initial model changeover ≤ 2 personnel within 8 hours (excluding first Pcs time; ramp-up time 8 hours) |
1.4 Main Equipment List
| No. | Equipment Name | Model | Qty | Unit | Remarks |
|---|---|---|---|---|---|
| 1 | Robot Cell Loading+Cell OCV Sorting Machine | / | 1 | Set | Barcode scanning + OCV testing |
| 2 | Module Conveyor Line | / | 1 | Pcs | Lifter + production line + module pallet |
| 3 | Manual Gluing and Stacking | 2 | Set | Cell adhesive application stacking | |
| 4 | Module Compress steel strapping | / | 2 | Set | Module automatic extrusion + manual steel strapping |
| 5 | Polarity detection | / | 1 | Set | Polarity detection |
| 6 | Pole addressing / Pole cleaning | / | 1 | Set | Pole addressing / Pole cleaning |
| 7 | Laser welding | / | 1 | Set | 6000W Laser |
| 8 | Weld Spot Inspection/Cleaning | / | 1 | Set | Manual Workstation + Vacuum Cleaner |
| 9 | Module EOL Test | / | 1 | Set | Module EOL Test |
| 10 | Module Off-line | / | 1 | Set | KBK Overhead Crane |
| 11 | PACK Conveyor Line | / | 1 | Pcs | Lifter + production line + module pallet |
| 12 | Liquid Cooling Plate Airtightness Test | / | 1 | Set | Liquid Cooling Plate Airtightness Test |
| 13 | Battery Pack EOL Test | / | 1 | Set | Battery Pack EOL Test |
| 14 | Pack Airtightness Test | / | 1 | Set | Pack Airtightness Test |
| 15 | PACK Finished Product Off-line | / | 1 | Set | KBK Overhead Crane |
Please contact us for detail:
Mr.John Yang Managing Director